Operating / Late-life Phase

Planning/Scope

Project management

Determine the strategic fit vs life-cycle of asset(s) in a company's portfolio to benefit from the most effective decom strategy.

  • Consider if others are more natural owners / operators at the late-life stage;
  • Divest sufficiently early for the asset(s) to still be attractive.

Determine the strategic fit vs life-cycle of asset(s) in a company's portfolio to benefit from the most effective decom strategy.

At late-life, align organisation & contracting strategy to maximise value.

  • Optimise both life-cycle costs and production;
  • Ensure organisational structure is incentivised / qualified to act on high value decom opportunities during late-life.

At late-life, align organisation & contracting strategy to maximise value.

Separating the topsides and substructure Decommissioning Programmes will increase timing flexibility in the topsides removal.

  • Particularly relevant if issues associated with substructure decommissioning (e.g. OSPAR derogation cases) could delay the Decommissioning Programme approval;
  • Areas of contention and  decommissioning options can be identified through early engagement with BEIS-ODU and stakeholder.

Separating the topsides and substructure Decommissioning Programmes will increase timing flexibility in the topsides removal.

Early stewardship engagement with the OGA can help identifying cost reduction opportunities.

  • OGA "Decom dashboards" are used to assess performance and identify areas where cost reductions could be possible, as achieved by others.

screen

Early stewardship engagement with the OGA can help identifying cost reduction opportunities.